HIGHWAY 75

Highway 75 from Plattsmouth to Murray is a project with the Nebraska Department of Transportation to widen 7 miles of the existing US 75 into a four-lane expressway.

After three decades of planning, the project was let in November of 2020, with Hawkins Construction as the successful low bidder. Work began in July of 2021, and has overcome several challenges including numerous underground utilities which needed to be relocated, labor shortages, and a global supply chain disruption.

The project is currently 75% complete, with a scheduled completion date of July 2024.

Project Quantities:
860,000 CY of excavation
5,900 LF of pipe
408,000 SY of paving and median surface.
6,000 tons of lime mixed into subgrade for stabilization.
3-span, 450-foot-long bridge over Union Pacific tracks.
7 box culverts and culvert extensions.
158 acres of erosion control.

Project Details

CLIENT:

Nebraska Department of Transportation

LOCATION:

Plattsmouth, NE

COMPLETED:

Ongoing

VALUE:

$45,000,000

CATEGORY:

Transportation Civil Utility