We expanded 168th Street from two to four lanes between W Dodge Road and W Maple Road. Median and left turn lanes were added, along with improvements to the intersection at Blondo Street. We worked with the City of Omaha to accelerate construction. We adjusted phasing to close Blondo for only 90 days to lessen the impact on area businesses. The entire project was completed in one year.
Project Quantities:
• 89,000 sq yards of 10-inch concrete pavement
• 99,500 sq feet of sidewalk
• 10,200 linear feet of 15- to 48-inch reinforced concrete pipe